Previous  Next  Close Window
     
Scipio Irrigation Ivie Creek Pipeline (Quest Project #5450230)
County/City/State: Millard County - Scipio, UT
Location / Site Directions: The project is located near Scipio Lake Reservoir in Milliard County, Utah.
Bids Close: 12/14/2017 04:00 PM MST
On-Line Bidding: Available
Bids Received By: Franson Civil Engineers
Estimated Value: $850,000 to $950,000 (engineer estimate)
Project Completion Date: 04/15/2018
Pre-Bid Meeting Information: A mandatory pre-bid conference will be held at 3:00 PM local time on December 6, 2017 at the Scipio City Building located at 160 N. State Street in Scipio, UT 84656.
Addenda:

2

Owner Project Number: CU.0133
Project Description: Work includes installation of about 3.5 miles of pipeline for an open-channel flow irrigation transmission pipeline in Scipio, Millard County, Utah. The entire pipeline will consist of 36-inch HDPE pipe of various pressure classes and will be installed near the existing ditch, through private properties, in the county road, and across a stream. Work also includes constructing an inlet structure, termination structure, and small turnouts, air valves, drains, and other pipe appurtenances. Owner will supply all pipe required for the transmission line.
Additional Description: Contact Layne Jensen with questions at 801-756-0309 or Ljensen@fransoncivil.com. Please review Project Q&A button for questions from bidders and responses.
Owner: Scipio Irrigation Company
PO Box 560121
Scipio , UT  84656
contact: Dallen Quarnberg
Soliciting Agent: Soliciting agent
Franson Civil Engineers
1276 South 820 East
Suite 100
American Fork,  UT 84003
ph: 801-756-0309
contact: Charity Mair
e-mail: cmair@fransoncivil.com

Project Documents: Bidding Documents will be available on November 29, 2017. The non-refundable purchase price is $25.00 for an electronic copy.
Quest eBidDocs™: Download delivery fee is $25.00, file size is 29.5 Mb.